NOTE: CFG, MacGrill, Sullivan’s, Torchy’s, Brookshire Bros, and NCL - All have controlled upgrades and will need to be approved by CORP first before pushing anything to their sites.

  • Carinos and Stacked will not ever be upgraded and will stay on their current legacy builds

5/23

Server Upgrades

  • Alger starts scheduling sites for Wave 1 (East Lake)

Wave 1 sites upgraded in the morning after EOD.

Sites will run on build and will be monitored by Support Team

5/30

Server Upgrades

  • Alger starts scheduling sites for Wave 2 (Dornoch)

Wave 2 sites upgraded in the morning after EOD.

Sites will run on build and will be monitored by Support Team

6/6

Server Upgrades

  • Alger starts scheduling sites for Wave 3 (Cypress)

Wave 3 sites upgraded in the morning after EOD.

Sites will run on build and will be monitored by Support Team

6/13

Server Upgrades

  • Alger starts scheduling sites for Wave 4 (Firestone if applicable and approved by corp)

  • Upgrade all remaining CORP sites after approval

Wave 4 sites upgraded in the morning after EOD.

Sites will run on build and will be monitored by Support Team

6/16

4.8.3 App Release