  • Unpack and assemble the the unit.
  • The unit should look like this once assembled.



  • Open the back rubber part of the CDU with a pair of tweezers and adjust the DIP Switches accordingly.
    #5 and #7 need to be put in the UP position. All other switches need to be DOWN



  • Next, connect the serial cable from the CDU to one of the ports on the Lantronix box. 
  • Verify the COM Port that you've assigned for this CDU and update in the ECM Peripherals as needed.
  • Assign the CDU to a device peripheral in ECM.
  • Once all of this is completed, you can need to run a DEPLOY to the site and the Customer Display Unit you've attached to the iPad Device will be sending orders to it.
    COMPLETED!