NOTE: CFG, MacGrill, Sullivan’s, Torchy’s, Brookshire Bros, and NCL - All have controlled upgrades and will need to be approved by CORP first before pushing anything to their sites.
Carinos and Stacked will not ever be upgraded and will stay on their current legacy builds
4/25 Server Upgrades
| 4/26 Wave 1 sites upgraded in the morning after EOD. | 4/27 Sites will run on build and will be monitored by Support Team | 4/28 | 4/29 | 4/30 | |
5/2 Server Upgrades
| 5/3 Wave 2 sites upgraded in the morning after EOD. | 5/4 Sites will run on build and will be monitored by Support Team | 5/5 | 5/6 | 5/7 | |
5/9 Server Upgrades
| 5/10 Wave 3 sites upgraded in the morning after EOD. | 5/11 Sites will run on build and will be monitored by Support Team | 5/12 | 5/13 | 5/14 | |
5/16 Server Upgrades
| 5/17 Wave 4 sites upgraded in the morning after EOD. | 5/18 Sites will run on build and will be monitored by Support Team | 5/19 4.8.3 App Release | 5/20 | 5/20 |