4/25

Server Upgrades

  • Alger starts scheduling sites for Wave 1 (East Lake)

4/26

4/27

4/28

4/29

4/30

5/2

Server Upgrades

  • Alger starts scheduling sites for Wave 2 (Dornoch)

5/3

5/4

5/5

5/6

5/7

5/9

Server Upgrades

  • Alger starts scheduling sites for Wave 3 (Cypress)

5/10

5/11

5/12

5/13

5/14

5/16

Server Upgrades

  • Alger starts scheduling sites for Wave 4 (Firestone)

  • Upgrade all remaining CORP sites after approval

5/17

5/18

5/19

4.8.3 App Release

5/20

5/20